1st Floor Renovation Project About to Begin

Posted on February 21, 2014 by

Starting Monday, February 24th, construction will begin on a $10 million renovation project for the first floor of the Domestic Terminal at BGR. Construction will take place in four phases, as to limit disruptions to passengers traveling to and from BGR. At no point will there be a disruption to air service due to the construction.

Starting Monday, Phase I begins. The focus of the phase is to update the escalators. These updates will make the escalators safer and more energy efficient.

One escalator will be shut down at a time for upgrades, with one escalator remaining for passenger use. During this phase, passengers needing additional assistance traveling between floors should use the elevator. The elevator located next to the Delta ticket counter on the 1st floor and the Coffee Shop located on the 2nd floor. There are also stairs next to the escalators for passengers to use.

Phase II, is scheduled to start this summer, while Phase I is still in progress. Below is more information about the construction and upgrades coming to BGR. Construction Infographic

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>